Former Harrah’s Tunica Resort Master Redevelopment (13615 Old Hwy 61 N, Robinsonville, MS): 1.3M sq. ft. covered footprint, 100 MW Entergy transmission intertie, high-pressure natural gas pipeline with on-site CCHP tri-gen, 63°F alluvial aquifer geo-exchange cooling, 50 MW behind-the-meter Solar/BESS, and self-funding fast-cashflow industrial assets.
Select a hotspot on the site map or browse the infrastructure modules below to inspect technical specifications and power allocation.
Retrofitted logistics warehouse shell (112,170 SF industrial cluster). Direct Liquid Cooling (DLC) cold plates, 50–100 kW/rack density, 8 in-row CDUs, dual 13.8 kV feeds, PUE <1.18.
14 to 34 heavy-duty 40-ft ISO hydro compute containers on concrete grade beams. Integrated 100ms dynamic curtailment for grid frequency response.
Behind-the-meter utility-scale solar PV array on repurposed Hale Irwin golf course acreage paired with lithium-iron-phosphate (LFP) storage for peak shaving ($0.030/kWh LCOE).
Ground lease to 184.5 MW AES Delta Wind project generating $330k/yr ground rent + contract off-take power under $0.035/kWh for up to 100 MW.
Interconnected high-pressure natural gas pipeline feeding aeroderivative gas turbines / reciprocating gensets. Waste heat recovery steam generators (HRSG) power absorption chillers for liquid cooling (>82% thermal efficiency; 6–9 month fast-track power).
Direct geothermal groundwater heat pump (GWHP) loop tapping the Mississippi River Alluvial Aquifer (constant 62°F–66°F). Delivers sub-1.08 PUE with zero evaporative water consumption, while 120°F+ coolant return pre-heats commercial laundry boilers and greenhouse thermal loops.
Official video tours and architectural/engineering renderings of the Harrah's Tunica resort, 100 MW substation, and AI data center halls.
Comprehensive video walkthrough of the 1,168-room resort complex, lakefront hotel towers, and convention facilities at 13615 Old Highway 61 N.
Detailed ground and aerial footage of the master parcel, showing the massive steel structures, access roads, and Mississippi delta topography.
High-density 52U rack rows with stainless steel coolant distribution manifolds, overhead medium-voltage busways, and dual redundant pump loops.
Dual-circuit 115/230 kV transmission step-down substation with utility-scale battery containers and rear 50 MW solar array.
Terrace & Veranda Hotel Towers, convention center, and the 50,000 sq. ft. commercial laundry plant servicing regional casino linen contracts.
Complete multi-vertical campus layout showing the integration of the 100 MW substation, modular compute containers, solar array, and resort hub.
Dual high-pressure gas pipeline interconnection, modular 20–100 MW aeroderivative turbines, waste-heat absorption chilling, and constant 63°F groundwater geo-exchange cooling.
The property is traversed by and adjacent to major interstate transmission corridors (Texas Gas Transmission / Trunkline) and an active Atmos Energy industrial high-pressure header that historically fired Harrah's commercial boiler plants and 50k SF laundry steam lines.
Simple-cycle power exhausts ~60% of fuel energy as heat. The Tunica CCHP plant routes turbine exhaust into Heat Recovery Steam Generators (HRSG) feeding single/double-effect lithium-bromide absorption chillers to produce zero-electric cooling.
Tunica County sits directly over the high-transmissivity Mississippi River Alluvial Aquifer (MRAA), delivering continuous 62°F–66°F (17°C) groundwater year-round for closed/open-loop geo-exchange cooling.
Comparative electrical headroom, acreage, and high-density compute suitability analysis across all major Tunica County resort properties.
| Property Name | Status | Acreage | Built Sq. Ft. | Power Capacity | DC Suitability |
|---|---|---|---|---|---|
| Former Harrah's / Grand (Subject Site) | Closed / Redeveloping | 2,100 AC | 1,300,000 SF | 20 – 100+ MW (115/230 kV) | Grade A+ (Optimal) |
| Sam's Town Hotel & Gambling Hall | Closed / Secondary | 85 AC | 550,000 SF | 5 – 15 MW (13.8 kV) | Grade B+ (Satellite Hub) |
| Resorts Casino Tunica | Shuttered (2019) | 40 AC | 200,000 SF | 3 – 8 MW (13.8 kV) | Grade B (Edge Only) |
| Tunica Roadhouse (Former Sheraton) | Casino Shuttered | 35 AC | 180,000 SF | 3 – 6 MW (13.8 kV) | Grade C+ (Constrained) |
| Gold Strike & Horseshoe Cluster | Active Gaming | 120 AC | 1,200,000+ SF | Fully Utilized (15-25 MW) | Grade D (Active Retail) |
| Fitz Tunica Casino & Hotel | Active Gaming | 55 AC | 350,000 SF | Active Load / River Bank | Grade F (Flood Zone) |
Simulate real-time megawatt load scaling, cooling PUE efficiency, and blended cost per kilowatt-hour across Entergy grid, Solar, and Wind.
Self-funding asset underwriting where fast-reactivating industrial assets service debt long before compute load is energized.
Commercial Laundry ($1.02M) + RV Park ($980k) + Wind Lease ($330k).
Passive NNN Shell Rent ($1.8M) + Pad Ground ($375k) + Power Throughput ($832k) + Ancillary.
100 MW Wholesale Colocation + 50 MW Solar PV + Veterans & Logistics Campus Tenants.